Friday January 2nd
Phone system migration
Saturday January 3rd 12:00 AM
Firewall software upgrades; brief interruptions as the traffic moves from the active firewall to the inactive firewall during reboots.
Tuesday January 6th
- Azure Virtual Desktop Cutover to new virtual desktop set; downtime expected if you are actively using a desktop
- Clearpass (Network Access Control system); no downtime expected
Wednesday January 7th
- Minor configuration change to all wired networking devices; no downtime expected
- Patching of our VMware servers; no downtime expected
Thursday January 8th 7:00 AM
Minor configuration change to all wired networking devices; no downtime expected
Friday January 9th 6:00 AM
Software upgrade on Classroom networking switches. Ten minutes of downtime is expected as the switches reboot.
Sunday January 11th 11:59PM - Monday January 12th 7:00 AM
Wireless networking software upgrade. This will be a rolling upgrade with 5-10 minutes of localized wireless outage while the wireless access points perform their upgrade and reboot.
Monday January 12th
- 12:00 AM, software upgrade to our enterprise storage; no downtime is expected
- 6:00 AM, Software upgrade on building wired networking switches. Ten minutes of downtime is expected as the switches reboot.
- 2:00 PM, Software upgrade to our enterprise backup infrastructure. No user facing downtime.
Tuesday January 13th 6:00 AM
Software upgrade on the data center wired networking switches. Ten minutes of downtime is expected as the switches reboot.
Wednesday January 14th 6:00 AM
Software upgrade on the aggregation wired networking switches. Ten minutes of downtime is expected as the switches reboot.
Thursday January 15th 6:00 AM
Software upgrade on the core wired networking switches. Ten minutes of downtime is expected as the switches reboot.
Check back for any updates to this schedule.